Retail center TPO in Centennial
Low-slope re-roof over a strip of six stores, done in phases around opening hours.

Material
TPO membrane
Roof size
140 squares
Pitch
1/12
Build time
9 days
01
— About this job
The problem
Six stores under one leaking flat roof, and no store willing to close for a day.
We split the job into nine phases and started at 6 AM so the loudest tear-off was done before opening. Every night the section in progress was sealed watertight. The new white membrane also cut the summer cooling load for the tenants.
What we did
- Phased tear-off around store hours
- Tapered insulation for drainage
- 60-mil white TPO membrane
- New flashing at 11 rooftop units